Timothy T. Day Overlook and Heritage Center Parkway Progress Report

Significant Activities This Week

Serra Stone finished the first the block wall on the north side of the Overlook, and began work on the next section. Branch applied the damp proofing required once the mortar was set.

The removal of the spoils pile near Rt.1 continued. Approximately 800 cubic yards of unusable material was hauled off this week.

WG Construction placed concrete at the base of the central area of the Overlook. They then began to form and set rebar for the lower sidewalk turn down.

Clark Electrical mobilized on site. They set and ran conduit for the in-wall light fixtures after the surveyors laid out the exact locations.

Next Week Activity Projection

  • Additional concrete wall will be formed and poured at the Overlook.
  • Serra Stone continues block work.
  • First delivery of field stone veneer.
  • Electrical rough-in as required.
  • Cut and fill operation restarts on Parkway from 17+00 to 23+00; completion of haul off of spoils pile at Rt.1 entrance.